May-12-09
ADDENDUM to RFP Issue Date to Pre-qualified firms
Schedule as follows:
Short list design-build firms/teams
Monday May 11th, 2009
Issue RFP to pre-qualified design-build firms/teams
Tuesday May 19th, 2009 (In observance of the Victoria Day Holiday)
Design Build RFP Closes
Monday July 6th, 2009
Award design-build contract
Monday July 20th, 2009
Substantial completion
Friday Sept 10th, 2010