New Fire Hall (South Station) – Project Update

New Fire Hall (South Station) – Project Update
Meloche Road & Simcoe Street, Amherstburg

The new South Station, located at Meloche Road and Simcoe Street, is designed to enhance emergency response services and provide a new functional space for our fire personnel and equipment. The project has seen several key milestones already completed.

Work Completed to Date:

  • Sitework preparation including stormwater collection system
  • Water service installation
  • Sanitary service installation
  • Hydro pole relocation
  • Temporary hydro service
  • Parking lot base
  • Building footings
  • Shop drawing submittals and material preparation

These foundational steps are crucial in supporting the structural integrity and long-term durability of the building.

What’s Next:

  • Completion of building footings and below grade walls
  • Backfill and interior plumbing
  • Installation of the superstructure
  • Ongoing site preparation
  • Construction of the superstructure is scheduled to begin in August 2025.

We appreciate the community’s continued interest and support as we move forward with this vital project. Once complete, the South Station will play a key role in protecting the safety and well-being of Amherstburg residents for years to come.